No Contract Name  Location Client Company Start Date End Date
1 205th Commando Site Facilites Construction Kandahar Weston Solutions Inc
AFCEE
Apr-2008 Jun-2009
2 Extension of Maintenance Shop Catwalk and Living Containers Bagram Air Field Kabul Inglett & Stubbs International Co Apr-2008 May-2008
3 General Construction Services in Kabul Air Port Kabul DynCorp International LLC 
USACE
May-2008 Oct-2008
4 Afghan National Army Communication Network, South Provinces Hilmand & Zabul Network Innovation Inc
U.S. DoD
May-2008 Jan-2009
5 209th Commando Battalion Compound and Forward Supply Depot Mazar-E-Sharif , Balkh CH2M HILL Constructions Co
AFCEE
Sep-2008 Jul-2010
6 Satellite Antenna Foundation Kabul Globecomm Systems, Inc USA Nov-2008 Jan-2009
7 Afghan National Army Strategic Communication Network, CMW Kabul Network Innovation Inc May-2009 Jul-2009
8 Communication Towers Remediation  Camp Phoenix & Eggers Kabul LGS Innovations LLC Aug-2009 Mar-2010
9 U.S. Embassy Mazar Consulate Project Mazar-E-Sharif, Balkh PAE U.S. DoS Jan-2010 Mar-2011
10 Compound Modification Project Kandahar IAP Dec-2010 Oct-2011
11 CLASS I Warehouse Expansion Project Kabul Lakeshore / USACE Apr-2011 Jul-2012
Total Program Revenue: $42,000,000.00 USD
COMPLETED PROJECTS
1. 205th Commando Site Facilities Construction
The scope of this project was to provide the planning and Construction of the Commando Compound Base in Kandahar for the Afghan National Police.
The project consisted of the Design and Construction of the following facilities:
  TYPE OF BUILDING QTY SQM AREA
Arm Storage 1 350 sm 350.00
Barracks Type A1 2 480.4 sm 960.80
Barracks Type A2 1 487.60 sm 487.60
Barracks Type B 5 416 sm 2,080.00
Battalion Head Quarters 1 350 sm 350.00
Battalion Storage 1 800 sm 800.00
BOQ Type A 1 70 sm 70.00
BOQ Type B 1 570 sm 570.00
Company Head Quarter 4 59.6 sm 238.40
DFAC 1 810 sm 810.00
Exercise Area 1 5525 sm 5,525.00
Fitness Center 1 300 sm 300.00
Gang Toilet 1 567 sm 567.00
Laundry 1 70 sm 70.00
Motor pool 1  3500 sm  3,500.00
Pol Storage 1 25 sm 25.00
Training Buildings 2 200 sm 400.00
Vehicle Maintenance Bay 1 400 sm 400.00
  TOTAL AREA 17,503.80
2. Extension of Maintenance Shop, Catwalk and Living Containers
This project consisted of constructing an extension to the Inglett and Stubs Maintenance Shop, and the addition to the existing catwalk of the Inglett and Stubs Living containers at Bagram Air Field.
3. General Construction Services in Kabul Air Port
The scope of this project was the relocation of DEA Hanger and construction of a new concrete pad for the Hanger, including options to construct an Office Building and a Storage Building.
The project consisted of the Design and Construction of the following facilities:
Airplane Hanger
Water Distirbution
Power Generation & Distribution
Assembly and Erecting of
 
100 x 60 m Apron
40 x 60 m Storage area
20 x 40 m Office Space
4. Afghan National Army Communication Network
The scope of this project was to provide network management, administration, maintenance and IT support, and long haul transmission, as defined in the contract specifications.
Building a state of the art OSP Communication Facility for the Afghan National Army
Connecting over 15km of 4 pair, 6 pair and 8 pair conduits in Qalat, Shorabak and Jalalabad.
Design and construct several hundred hand holes and manholes

 

All the Designs and Construction Codes were in compliance with International Building Codes and the requirements of Network Innovation Inc and U.S. DoD.
5. 209th Commando Battalion Compound and Forward Supply Depot
The scope of this project was to provide the planning and Construction of the Commando Compound Base in Mazar-E-Sharif for the Afghan National Police.
The project consisted of the Design and Construction of the following facilities:
  TYPE OF BUILDING QTY SQM AREA
Arm Storage 1 349.68 sm 349.68
Barracks A1 2 480.40 sm 960.80
Barracks A2 1 523.20 sm 523.20
Barracks B 5 447.60 sm 2,238.00
Battalion Head Quarter 1 381.89 sm 381.89
Battalion Storage 1 800.88 sm 800.88
Base Officer Quarters 1 662.03 sm 662.03
Base Officer Quarters 1 688.94 sm 688.94
Base Officer Quarters 1 95.34 sm 95.34
Base Officer Quarters 1 576.74 sm 576.74
Company Head Quarter 4 58.40 sm 233.60
DFAC 1 809.99 sm 809.99
DFAC in FSD Site 1 1794 sm 1,794.00
Enlisted Barracks 1 583.41 sm 583.41
Existing Warehouse 1 1555.35 sm 1,555.35
Fitness Center 1 304.80 sm 304.80
Fuel Storage 1 602.00 sm 602.00
Gant Latrine 1 637.39 sm 637.39
Guard house 2 9.00 sm 18.00
Motor Pool 1 3907.99 sm 3,907.99
NCO/Enlisted Barracks 1 665.62 sm 665.62
Pol Storage 1 25 sm 25.00
SNCO/Officer Barracks 1 396.96 sm 396.96
Solid Waste 1 9.00 sm 9.00
Training Buildings 1 400.00 sm 400.00
Vehicle Maintenance Bay 1 400.00 sm 400.00
Vehicle Maintenance with Class 1 Storage 1 991.67 sm 991.67
  TOTAL AREA 20,612.28
All the Designs and Construction was in compliance with International Building Codes and the requirements of CH2M Hill and AFCE.
6. Satellite Antenna Foundation
This project consisted of Engineering, Furnishing, Installing and testing of the following Satellite Antenna components:
ASC signal 9.3m 4.port circular polarized antenna
1:2 redundant LNA System
1:2 redundant 400w TWTA system
Dual 8-way transmit combiners
Dual 16-way receive dividers
Wave guide pressurization and dehydrator
Transmit and receive RF IFLs and overhead gantry
Civil Works
Logistics
7. Afghan National Army Strategic Communication Network, CMW
Fiber optic cable OFC running
Trenching and lay down the conduits for outside plan copper and OFC cable
Provide and install hand holes and manholes
All cable pulling on site plan
Installation of communication pull box and cabinets
Providing all grounding systems
8. Communication Towers Remediation
The scope of this project was to remediate physical and operational deficiencies associated with two communications towers belonging to the U.S. Government located at camp Eggers and camp Phoenix.

Grounding and LPS were not properly installed on the system and the requirement was to repair this without disconnecting the communication.
9. U.S. Embassy Mazar Consulate Project
The scope of this project consisted of converting an existing Hotel structure to accommodate the U.S. Consulate in Mazar. This included the replacement of all infrastructure including water, sewer, electrical and communications facilities while maintaining the Architectural and structural systems of the building in accordance with U.S. Building Codes.
 
10. Compound Modification Project


This project consists of the following key elements:
Demolition of existing structures and facilities
Installation and synchronization of two 900KVA Generators.
Installation of below grade fuel supply system
Construction of generator building.
Provision of temporary power to ensure constant uninterrupted energy source to pre-existing compound facilities for the duration of the entire project.
11. CLASS I Warehouse Expansion Project
The project consists of the design and construction of nine buildings, a Vehicle Refueling Point with Fuel Storage, two guard towers, and approximately 565m of Sniper Screen on perimeter fence, demolition of an existing guard tower and barracks and 845m2 of existing roadway, construction of additional roads, sidewalks, and parking areas. Also included is connection of the new structures to existing base utility systems (water, sanitary, communications, drainage, and electrical).